Task Name

Start

Finish

% Work Complete

2.1 Project Management & Coordination

6-Mar-00

01-Jun-01

100%

2.1.1 Project Management Plan

06-Mar-00

17-Mar-00

100%

2.1.2 Kickoff Meeting

17-Mar-00

17-Mar-00

100%

2.1.2 Project Coordination

06-Mar-00

01-Jun-01

100%
2.2 Information Collection & Management

20-Mar-00

12-May-00

100%

2.2.1 Literature Search

20-Mar-00

21-Apr-00

100%
2.2.2 Eval. & Define Deficiencies of Exist. Data

27-Mar-00

12-May-00

100%
2.3 Field Work & Data Analysis

20-Mar-00

27-Oct-00

100%

2.3.1 Field Work

20-Mar-00

09-Jun-00

100%
2.3.2 Biological Resources

20-Mar-00

21-Jul-00

100%
2.3.3 Water Quality Analysis

03-Apr-00

16-Oct-00

100%
2.3.4 Land Use Inventory

20-Mar-00

07-Apr-00

100%
2.3.5 Surveying

22-May-00

14-Aug-00

100%
Prepare & Submit Watershed Pollutant Loading Interim Report (WPLIR)

01-Feb-01

14-Feb-01

100%
Rev. & Approv. WPLIR

15-Feb-01

01-Mar-01

100%
2.3.6 GIS Database

20-Mar-00

04-Aug-00

100%

2.4 Watershed Modeling

10-Apr-00

9-Oct-00

100%

Hydrologic Model Development

10-Apr-00

26-May-00

100%
Hydraulic Model Development

17-Jul-00

22-Sep-00

100%
Model Calibration

25-Sep-00

9-Oct-00

100%
Prepare & Submit Interim Report

9-Oct-00

25-Oct-00

100%
Review & Approval of Interim Report

25-Oct-00

9-Nov-00

100%
Prepare & Submit FEMA LOMR Application

01-Mar-01

18-Apr-01

0%
FEMA LOMR Application Review & Approval

18-Apr-01

17-Jul-01

0%
2.5 Identification of Problems & Potential Solutions

04-Sep-00

10-Nov-00

100%

2.5.1 Evaluate Existing Conditions

9-Oct-00

25-Oct-00

100%
2.5.2 Develop & Eval. Potential Solutions

02-Oct-00

10-Nov-00

100%
2.6 Evaluation & Prioritization of Potential Solutions

13-Nov-00

31-Jul-01

100%

2.6.1 Eval. & Prioritize Potential Solutions

13-Nov-00

15-Mar-01

100%
2.6.2 Preliminary Report

13-Nov-00

14-Feb-01

100%
Rev. & Approv. of Preliminary Report

15-Feb-01

15-Mar-01

100%
2.6.3 Draft Final Report

19-Mar-01

30-Mar-01

100%
Rev. & Approv. of Draft Final Report

19-Apr-01

30-Apr-01

100%
2.6.4 Final Report

02-Apr-01

30-Apr-01

100%
2.7 Coordination with Permitting Agencies

08-Jan-01

08-Feb-01

100%
2.8 Presentations. Public Meetings & Technical Liaison

27-Apr-00

15-Jun-01

100%

Meeting with SWFWMD Permitting Dept.

25-Sep-01  11:00am

 
Public Information Meeting No. 2

31-Jan-01

 
Public Information Meeting No. 3

TBA

 
Presentation to City Council

TBA

 
Presentation to SWFWMD & Basin Board No.1

TBA

 
Presentation to SWFWMD & Basin Board No. 2

TBA

 